Bristol Myers Squibb – BDB Building
Devens, MA
Plumbing
Install double contained underground piping in Biological Development Building (BDB) and Clinical Manufacturing Building (CMB). Install Process waste, lab gases (CA, N2, Vac, CO2, Lab RODI piping, Lab RODI Skid, domestic water, safety shower system, water heater, sanitary plumbing, Air compressor, Vacuum pump, ph neutralization system, Liquid N2 system, Gaseous N2 manifold in BDB. BDB is a 4 floor building with 2 floors of lab space, one for future and one for mechanical systems. 3rd floor fit out.
- Owner – Bristol Myers Squibb
- Duration – 24 months
- Architect – ARC
- General Contractor – Lend Lease
- Combined Contract – $12 million